Work in days / hours

P

Pierre ANDRIEU

Hello,

When I work on a local project the work of the resources is in days but when
I record a project on the server and I extract it, the work of the resources
is indicate in hour (for the summary by resource). Can I have it in days ?

Thank you very much.


Peter
 
M

Mike Glen

Hi Peter,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
M

Mike Glen

Sorreeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeey :( I was in the wrong newsgroup
myself, not you!

Perhaps someone will answer as I don't have a server.

Mike Glen
Project MVP
 
Top