Is it possible to show the work in days in the Project center instead of work in hours? Yves
Y Yves Nov 23, 2004 #1 Is it possible to show the work in days in the Project center instead of work in hours? Yves
M Michael McGinley Nov 23, 2004 #2 Open Project Pro (or Project) Go to Tools, Options, Schedule Change Work is entered in: "Days" Click the set as default button. Is using in an EPM enviornment, make sure you have the Enterprise Global Checked Out. Hope this helps.
Open Project Pro (or Project) Go to Tools, Options, Schedule Change Work is entered in: "Days" Click the set as default button. Is using in an EPM enviornment, make sure you have the Enterprise Global Checked Out. Hope this helps.
Y Yves Nov 23, 2004 #3 Sorry but it didn't work. It seems that there is no relation between the default settings in Project Pro and the data displayed in PWA Project Center. Do you have another solution? Thanks Yves
Sorry but it didn't work. It seems that there is no relation between the default settings in Project Pro and the data displayed in PWA Project Center. Do you have another solution? Thanks Yves