Work in days in Project Center

Y

Yves

Is it possible to show the work in days in the Project center instead of work
in hours?

Yves
 
M

Michael McGinley

Open Project Pro (or Project)

Go to Tools, Options, Schedule

Change Work is entered in: "Days"

Click the set as default button.

Is using in an EPM enviornment, make sure you have the Enterprise Global
Checked Out.

Hope this helps.
 
Y

Yves

Sorry but it didn't work. It seems that there is no relation between the
default settings in Project Pro and the data displayed in PWA Project Center.
Do you have another solution?

Thanks

Yves
 