work not summarizing correctly

L

LML

I'm working with Project 2003 and am finding that work is not summarizing
correctly. Here's an example of what I am seeing with 1 resource at 100%

Task Name / work / duration
1. User feedback / 20 days / 10 days
1.1. implement feedback on entry / 6 days / 6 days
1.2 implement feedback on approvals / 4 days / 4 days

The duration is summarizing correctly, but the work is additional effort and
I can't figure out why since the individual tasks are accurate.

Any help?

Thanks!
 
M

Mike Glen

Hi LML,

Welcome to this Microsoft Project newsgroup :)

It sounds like you have resources assigned to the summary task and are thus
being counted twice. You might like to see FAQ Item: 49 on summaries.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 