L
LML
I'm working with Project 2003 and am finding that work is not summarizing
correctly. Here's an example of what I am seeing with 1 resource at 100%
Task Name / work / duration
1. User feedback / 20 days / 10 days
1.1. implement feedback on entry / 6 days / 6 days
1.2 implement feedback on approvals / 4 days / 4 days
The duration is summarizing correctly, but the work is additional effort and
I can't figure out why since the individual tasks are accurate.
Any help?
Thanks!
correctly. Here's an example of what I am seeing with 1 resource at 100%
Task Name / work / duration
1. User feedback / 20 days / 10 days
1.1. implement feedback on entry / 6 days / 6 days
1.2 implement feedback on approvals / 4 days / 4 days
The duration is summarizing correctly, but the work is additional effort and
I can't figure out why since the individual tasks are accurate.
Any help?
Thanks!