Y
Yawningdog
Hi there.
I have a construction project and I would like to allocate different
tasks to named workers as and when they have finished their previous
tasks.
Here is an example. I have 3 x labourers, Bill, Ed, and Will. They all
have the same skill sets and are paid the same amount per day. I have
entered them into my resource pool as a single resouce, "Labourers",
units 300%.
However, I have many different tasks that are taking place at the same
time over several days. Some of these tasks require only one labourer,
whilst others may require 2 or 3 labourers. When I allocate the
labourers to each task in MS Project it gives me a percentage beside the
labourers which doesn't help me to schedule or communicate with my
workers what each person should be doing now or next.
Alternatively, I have tried to create 3 x separate workers in the
resource pool, Bill, Ed, and Will, and allocate units of 100% each. I
don't care who does what piece of work as the skill requirements are the
same, so I allocate all three to each task. But then MS Project will
surely assume that I want all three of them to work on the tasks even if
the tasks may only need one person.
My final option is to allocate each worker (by name) to each task
separately, but then that is time consuming and I am unable to calculate
the most efficient distribution of their time.
Surely I must be missing something. Is it possible to group a series of
named workers under a skillset and ask MS Project to allocate them to
the tasks that meet that skillset?
Thanks, and sorry for the length of this message.
I have a construction project and I would like to allocate different
tasks to named workers as and when they have finished their previous
tasks.
Here is an example. I have 3 x labourers, Bill, Ed, and Will. They all
have the same skill sets and are paid the same amount per day. I have
entered them into my resource pool as a single resouce, "Labourers",
units 300%.
However, I have many different tasks that are taking place at the same
time over several days. Some of these tasks require only one labourer,
whilst others may require 2 or 3 labourers. When I allocate the
labourers to each task in MS Project it gives me a percentage beside the
labourers which doesn't help me to schedule or communicate with my
workers what each person should be doing now or next.
Alternatively, I have tried to create 3 x separate workers in the
resource pool, Bill, Ed, and Will, and allocate units of 100% each. I
don't care who does what piece of work as the skill requirements are the
same, so I allocate all three to each task. But then MS Project will
surely assume that I want all three of them to work on the tasks even if
the tasks may only need one person.
My final option is to allocate each worker (by name) to each task
separately, but then that is time consuming and I am unable to calculate
the most efficient distribution of their time.
Surely I must be missing something. Is it possible to group a series of
named workers under a skillset and ask MS Project to allocate them to
the tasks that meet that skillset?
Thanks, and sorry for the length of this message.