Hello,
We have a master plan linked to 6 sub-projects. The master is just to serve
as a global view with the main project information. We created the tasks in
the master to be summary task of the actual task in the sub-projects. MS
Project is caculating and showing the % COmplete at the summary level, but it
will not calculate/total the Work. The summary always displays zero, even
when you can view the predecessor task that is grayed out has actual values
for the Work.
Anyone know how to make sure all of the summary data is calculating?
We have a master plan linked to 6 sub-projects. The master is just to serve
as a global view with the main project information. We created the tasks in
the master to be summary task of the actual task in the sub-projects. MS
Project is caculating and showing the % COmplete at the summary level, but it
will not calculate/total the Work. The summary always displays zero, even
when you can view the predecessor task that is grayed out has actual values
for the Work.
Anyone know how to make sure all of the summary data is calculating?