Work unit "S" Curve

A

armchairandy

Hi

I currently export planned vs actual progress to an excell file where i
produce an "S" curve of planned vs actual - accumulated work done chart. Can
MSP 2000 produce anything similar within itself ??


Andrew
 
J

John

Andrew,
No, not directly, but a VBA macro can be used to automatically export
and format the data you want. If you do not have VBA experience, we can
help you get started.

Hope this helps.
John
Project MVP
 