Work Variance Post

P

PMPFred

Good day Mooney,

If you are refering to the portfolio analyzer section of
PWA, I believe you need to setup the specific view you are
using to use the "day" info of the time dimension. Not
sure how to translate that into more comprehensive
english, however I'll guide you to the area so you can
play around with the settings:
1) PWA / Admin
2) Manage views / scroll down to "Portfolio analyzer" and
select either a specific view to edit or anyone
3) select Modify View
4) find the "Field list" button (or right-click in the
view to obtain the pop-up and choose "field list")
5) scroll down until you find the "Time" dimension, expand
it, and you will see "days"
6) Click-hold, drag & drop "days" into the view,
7) Save & voila!

Cheers
 
Top