The formula
=WORKDAY(A1,A2,)
Produces the result 1/7/2005 for me when cell A1 has 1/1/2005 in it and cell
A2 has 5 in it.
Perhaps you need to check the way the cells are formatted. Mine are
formatted as dates (except A2 with the 5 which is formatted general).