D
Dave
I have a pool of 7 developers with a manager. I don't want to assign work to
the 7 developers directly but assign them all to the manager and have him
delegate. How is the best way to do this?
Right now, I have a generic "developer" at 700% allocation units. My team
allocates tasks to this one resource and levels appropriately. Then we pass
these tasks to the development lead and they redistribute as they see fit.
However, ideally we allocate these tasks to the development lead and they
delegate to their team members. But this means we set our development
manager at 700% which seems wrong.
So, how do we assign and level 7 resources but then have one person delegate
them?
Dave
the 7 developers directly but assign them all to the manager and have him
delegate. How is the best way to do this?
Right now, I have a generic "developer" at 700% allocation units. My team
allocates tasks to this one resource and levels appropriately. Then we pass
these tasks to the development lead and they redistribute as they see fit.
However, ideally we allocate these tasks to the development lead and they
delegate to their team members. But this means we set our development
manager at 700% which seems wrong.
So, how do we assign and level 7 resources but then have one person delegate
them?
Dave