working days to calendar days

M

Mike Mc

Does anyone know how to change program to show calendar
days on the chart instead of working days.

In other words when I put 30 days in the "Duration"
column, I want the timeline to show approx 1 month, not 6
five day work weeks.

Thanks in Advance

Mike Mc
 
J

Jan De Messemaeker

Hi,

Tools, Change Working time, for the standard project calendar select the 7
days calendar.
When later you will use resources (who probably won't work 7 days a week)
you can reflect that in their calendar.

HTH
Jan De Messemaeker Project MVP
 