C
carolyn
I want to see the effects on my end date if some of my tasks are deleted or
if some tasks start earlier than currently planned. I was thinking of doing
this by working offline. My thought process is;
1. Save Offline
2. Open project by signing in, and choosing work offline
3. Modify as required and make some decisions
My sticking point is here. How do I proceed if I do NOT want to save those
changes?
The way I see it my project would be offline but I need the status moved to
online without actually updating the data.
Any thoughts?
if some tasks start earlier than currently planned. I was thinking of doing
this by working offline. My thought process is;
1. Save Offline
2. Open project by signing in, and choosing work offline
3. Modify as required and make some decisions
My sticking point is here. How do I proceed if I do NOT want to save those
changes?
The way I see it my project would be offline but I need the status moved to
online without actually updating the data.
Any thoughts?