L
Luke
How can I set up a calendar for a 4 days on 4 days off roster as the days
worked are different each week? eg Monday to Thursday then the next week is
Tuesday to Friday without editing every day of the year
worked are different each week? eg Monday to Thursday then the next week is
Tuesday to Friday without editing every day of the year