M
MackT
Hi All,
I am a newbe to MS Project so maybe this is a simple question to some
of you.
I have been struggling with something in Project that I'm hoping some
of you've ran across already. I need to setup tasks that show the
actual work time of the task but spread out over a few weeks. For
example, I need to setup a task where I give someone two weeks to do it
but it will only take them three hours. I don't care when they work
their three hours in those two weeks but I want to show that they had it
assigned on May 1 and it needs to be complete by May 14th and it took
three hours of effort. Is this possible?
Thanks
MackT
I am a newbe to MS Project so maybe this is a simple question to some
of you.
I have been struggling with something in Project that I'm hoping some
of you've ran across already. I need to setup tasks that show the
actual work time of the task but spread out over a few weeks. For
example, I need to setup a task where I give someone two weeks to do it
but it will only take them three hours. I don't care when they work
their three hours in those two weeks but I want to show that they had it
assigned on May 1 and it needs to be complete by May 14th and it took
three hours of effort. Is this possible?
Thanks
MackT