Hi,
I am having this problem and would really appreciate if I
could get any help with it.
For some reason, when I open projects in Microsoft Project
2003, and go to the Resource sheet, and then display both
ID and Unique ID columns they show the same numbers. It
happens even in cases when I add a couple of resources,
remove some of them and add new ones. Once I save the
project, close it and then reopen, the ID-s are identical.
In the help Project has this for Unique ID "As you add
resources, Project assigns a unique number to each
resource within the project. This number is unique in that
it is never rearranged or reused if the resource is moved
or deleted."
To make it more complicated, if I query the msp_resources
table then in the table the res_uid field is unique and
different. It seems that somehow project displays ID
values under Unique ID in the Resource Sheet.
The main reason why this presents a big problem for me is
that sometimes when I delete resources that don't have any
tasks assigned, this action removes assignments from other
resources, since the Project has mixed up Unique ID-s and
ID-s.
Thanks,
Predrag
I am having this problem and would really appreciate if I
could get any help with it.
For some reason, when I open projects in Microsoft Project
2003, and go to the Resource sheet, and then display both
ID and Unique ID columns they show the same numbers. It
happens even in cases when I add a couple of resources,
remove some of them and add new ones. Once I save the
project, close it and then reopen, the ID-s are identical.
In the help Project has this for Unique ID "As you add
resources, Project assigns a unique number to each
resource within the project. This number is unique in that
it is never rearranged or reused if the resource is moved
or deleted."
To make it more complicated, if I query the msp_resources
table then in the table the res_uid field is unique and
different. It seems that somehow project displays ID
values under Unique ID in the Resource Sheet.
The main reason why this presents a big problem for me is
that sometimes when I delete resources that don't have any
tasks assigned, this action removes assignments from other
resources, since the Project has mixed up Unique ID-s and
ID-s.
Thanks,
Predrag