Hi everyone,
I've spent the better part of the morning reading all the posts regarding
administrative projects, and it seems to be a hot topic.
What I can't find for administrative projects, is a way to allocate either
an hourly figure (or a percentage if I must) to each of our resources for a
particular admin task. For example:
Peter, Paul and Mary each use 1 hour daily, to maintain system "X". Peter
and Paul also put aside 2 hours daily to maintain system "Y".
Similarly, John is only available 50% of the time for project work, while
the other half of his time is spent on various administrative projects.
Whenever I attempt to allocate this time, PS2003 changes either the start or
finish dates for these tasks. We want the tasks daily, ongoing tasks for
each quarter.
What concept am I missing?
Thank you,
RAS
I've spent the better part of the morning reading all the posts regarding
administrative projects, and it seems to be a hot topic.
What I can't find for administrative projects, is a way to allocate either
an hourly figure (or a percentage if I must) to each of our resources for a
particular admin task. For example:
Peter, Paul and Mary each use 1 hour daily, to maintain system "X". Peter
and Paul also put aside 2 hours daily to maintain system "Y".
Similarly, John is only available 50% of the time for project work, while
the other half of his time is spent on various administrative projects.
Whenever I attempt to allocate this time, PS2003 changes either the start or
finish dates for these tasks. We want the tasks daily, ongoing tasks for
each quarter.
What concept am I missing?
Thank you,
RAS