I discovered this by chance, and have done a little testing - it seems to
work - but haven't seen it referred to anywhere in documentation.
If you edit the My Tasks webpart, and on the "PWA" settings tick the box
that says "Hours per day" you will get 7 days worth of columns, and the
'previous' and 'next' icons are enabled so you can scroll backwards and
forwards. The daily columns replace the single "Progress" column. The
updates go to the project manager exactly as if the Details page had been
used.
Scary - we're almost aftraid to use it because we haven't seen it mentioned
anywhere and it may disappear again!
work - but haven't seen it referred to anywhere in documentation.
If you edit the My Tasks webpart, and on the "PWA" settings tick the box
that says "Hours per day" you will get 7 days worth of columns, and the
'previous' and 'next' icons are enabled so you can scroll backwards and
forwards. The daily columns replace the single "Progress" column. The
updates go to the project manager exactly as if the Details page had been
used.
Scary - we're almost aftraid to use it because we haven't seen it mentioned
anywhere and it may disappear again!