Budget Baselines

C

c.tambone

Hello,

I would like to use a Baseline Budget field (for example Baseline 5
Budget Work), to enter manually in the Resource Usage page the amount
of hours requested fo that specific resource (in addition to the
normal usage of the Busget Work field) and I would like to view that
information in a Data Analysis view. I have already tried and if I do
not save the baseline of my selected field, the pivot table does not
include that amount. The problem is that if I save the baseline of my
selected field, I will loose all changes and info manually inserted.
Is there a workaround of your knowledge.
Thanks,
Claudia
 