A
Anna
Good morning,
I am currently working in Project 2007.
I have developed a schedule, added resources and costs, and saved the
baseline. The cost under view/tables /more tables/earned value all add up
nicely. When moving out the status date to 1 month out and then updating by %
Complete, the cumulative totals all work out as well.
When I go to Earned Value over Time report in visual reports, the totals all
add up in the assignment usage with/EV looks good.
The problem I have is I want to be able to see the planned value for the
entire length of the project, and than Earned value by % complete. The report
will show me earned and planned value and then it takes a nose dive when
values are 0. I'm guessing that is caused by the staus date. It's not showing
as a cumaltive total (level line until it's updated) Please let me know how I
can show the planned value for the entire project and be able to show both
planned and earned value all as cumulative totals so my chart won't take a
nose dive.
Respectfully,
Anna
I am currently working in Project 2007.
I have developed a schedule, added resources and costs, and saved the
baseline. The cost under view/tables /more tables/earned value all add up
nicely. When moving out the status date to 1 month out and then updating by %
Complete, the cumulative totals all work out as well.
When I go to Earned Value over Time report in visual reports, the totals all
add up in the assignment usage with/EV looks good.
The problem I have is I want to be able to see the planned value for the
entire length of the project, and than Earned value by % complete. The report
will show me earned and planned value and then it takes a nose dive when
values are 0. I'm guessing that is caused by the staus date. It's not showing
as a cumaltive total (level line until it's updated) Please let me know how I
can show the planned value for the entire project and be able to show both
planned and earned value all as cumulative totals so my chart won't take a
nose dive.
Respectfully,
Anna