alper gurbuz
Hi, the project 2007 doesnt seem to calculate the earned value correctly. If you mark a task as complete before the estimated due date , the earned value is caluculated as the same value as the planned value. You can not have the earned value to be greater than the planned value at any given time. Unless I am doing something wrong, this seems to me like a bug . Any comments or help ?