P
Peteupnorth
I use formulas and graphical indicators to show update status of tasks :
Red : Past the finish date and not complete
Yellow : Past start date with zero%
Maroon : Past start date with some progress
Blue : Completed
Green : Not yet due to start
I would like to add in an indicator to identify tasks that are due to start
within the next 7 days but cannot get any formula to work. Can any one help
with this please. I am using a Number field for the indicators described
above.
Red : Past the finish date and not complete
Yellow : Past start date with zero%
Maroon : Past start date with some progress
Blue : Completed
Green : Not yet due to start
I would like to add in an indicator to identify tasks that are due to start
within the next 7 days but cannot get any formula to work. Can any one help
with this please. I am using a Number field for the indicators described
above.