M
milrock
Hi Everyone,
I'm having an issue at a client that I am trying to work out by using
material resources but I am not getting the behaviour that I thought
as variable material resources seem to act completely the same as
fixed materials.
I have a client that has a two production floors (factories). When
each project is started it will use a certain percentage of floor
space is square feet per day until the project is complete. For
example, a project is using 2000 sq/ft per day over a duration of 50
days which means a total square footage usage of 100,000 sq/ft for the
entire duration of the project. But if the project is delayed to say
70 days duration the total square footage used for the entire project
would actually be 140,000 square feet. In Microsoft Project, the
daily consumption rate is lowered when the duration is increased. I
need to be able to keep the daily consumption rate the same then
increase the duration and have the daily consumption rate extend out
to the new duration instead of decreasing the daily consumption as the
duration is increased.
Does anyone have any ideas on how I could accomplish this? Should I
just be using a work resource to accomplish this? Using a work
resource to track this will throw off all of the work numbers for
every project that has a floor space resource in it.
Please assist and thanks for your help.
Regards,
milrock
I'm having an issue at a client that I am trying to work out by using
material resources but I am not getting the behaviour that I thought
as variable material resources seem to act completely the same as
fixed materials.
I have a client that has a two production floors (factories). When
each project is started it will use a certain percentage of floor
space is square feet per day until the project is complete. For
example, a project is using 2000 sq/ft per day over a duration of 50
days which means a total square footage usage of 100,000 sq/ft for the
entire duration of the project. But if the project is delayed to say
70 days duration the total square footage used for the entire project
would actually be 140,000 square feet. In Microsoft Project, the
daily consumption rate is lowered when the duration is increased. I
need to be able to keep the daily consumption rate the same then
increase the duration and have the daily consumption rate extend out
to the new duration instead of decreasing the daily consumption as the
duration is increased.
Does anyone have any ideas on how I could accomplish this? Should I
just be using a work resource to accomplish this? Using a work
resource to track this will throw off all of the work numbers for
every project that has a floor space resource in it.
Please assist and thanks for your help.
Regards,
milrock