Report / Graphs for Schedule Tracking.

R

robertpoddar

Hi,
I am using the MS Project 2003 Standard version. I would like to generate a
graphical report showing the progress of the project, i.e. baseline versus
actual.
Whatever schedule tracking report is built into the MS Project, doesn't
suffice my needs.

Anything that i am missing?.
 
R

robertpoddar

Hi Rob,
Thanks for the quick feedback. The graphical report that i have in mind, is
to show the actual status of the project versus the baseline. When i present
the report, to my management, it would give them an idea as to where we are
in the project.
The built-in reports in MS Project, just shows in 3 columns the list of
tasks, baseline start and the actual start.

I hope i am able to provide some more clarity.
 
J

Jim Aksel

Try searching on "Earned Value"
You can export EV Data to Excel and have all the graphs you desire.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
R

robertpoddar

Hi Jim,
Thanks a lot for the support/help. I guess i am now closing in on what i
want.
 