E
ET902
Here is a problem that I have tried to resolve many tomes myself but have
finally given up, so it's time to ask the gurus.
Say I have a piece of test equipment that several groups uses throughout the
life of a project. I want to know whenever that equipment becomes
overallocated. If I make it a work resource then I get the overallocation,
but I don't want the resource to show up as hours of work. If I make the
equipment a material resource it will not show as an overallocation. I want
it to show up as overallocated, but not show hours work.
Any suggestions?
finally given up, so it's time to ask the gurus.
Say I have a piece of test equipment that several groups uses throughout the
life of a project. I want to know whenever that equipment becomes
overallocated. If I make it a work resource then I get the overallocation,
but I don't want the resource to show up as hours of work. If I make the
equipment a material resource it will not show as an overallocation. I want
it to show up as overallocated, but not show hours work.
Any suggestions?