Showing reports based upon baseline 3.

L

Lee

1. How do I know which baseline my Gantt is using?

2. How do I know which baseline my Reports are using?

To explain more: When I open my MS Project File and go to Tools/Tracking...I
see that the baseline is set to baseline one. This leads me to believe that
MS Project is basing reports off of baseline one, correct? I do not want
this. What I do want is baseline 3 to be what MS Project Uses. Can you tell
me how to make this happen please?

Thank you!
 
J

Jim Aksel

Tools/Options/Calculation (tab). On that tab, select the button for Earned
Value...
In the dialog that opens you are allowed to select which baseline is used
for calculation purposes. The other choice on that form is the EV method
applied as default to new tasks (%Complete or Physical%Complete).

EV Methods for tasks already in the schedule model are available under the
advanced tab of the Project Information form.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 