K
Kevinexzim
I want to keep an eye on schedule slippage on a project.
Is there a simple equivalent to SPI (Schedule Performance Index = ratio of
work performed/work scheduled) using just Duration, without involving
Resources, Work and Costs?
MS Project wants to use Work, Resources and Costs to calculate SPI =
BCWP/BCWS (Budgeted Cost of Work Performes/Budgeted Cost of Work Scheduled).
Some of my projects are simply task-based and scheduled in Duration
(workdays) - without Resources, Work or Costs.
Even for those projects that do have Resources, Work and Costs, I would like
SPI based simply on Duration.
I use MS Project 2002.
Thanks.
Is there a simple equivalent to SPI (Schedule Performance Index = ratio of
work performed/work scheduled) using just Duration, without involving
Resources, Work and Costs?
MS Project wants to use Work, Resources and Costs to calculate SPI =
BCWP/BCWS (Budgeted Cost of Work Performes/Budgeted Cost of Work Scheduled).
Some of my projects are simply task-based and scheduled in Duration
(workdays) - without Resources, Work or Costs.
Even for those projects that do have Resources, Work and Costs, I would like
SPI based simply on Duration.
I use MS Project 2002.
Thanks.