S
Steve Scott
I have eg 5 milestones which rollup to a normal summary bar. The 5th
milestone date obviously determines the Summary Bar's finish date. I would
like to be able to "shorten" the length of the summary bar so that its finish
date is equal to the date of the 4th milestone which is earlier than the 5th.
Can this be done automatically from the milestone row itself or do I have to
add in a custom Finish date at the Summary level and add in the date manually
and then modify the bar style accordingly?
Thanks in advance.
milestone date obviously determines the Summary Bar's finish date. I would
like to be able to "shorten" the length of the summary bar so that its finish
date is equal to the date of the 4th milestone which is earlier than the 5th.
Can this be done automatically from the milestone row itself or do I have to
add in a custom Finish date at the Summary level and add in the date manually
and then modify the bar style accordingly?
Thanks in advance.