The summary bar is not displaying progress, once a milestone is co

C

Carlo

I'm updating my milestone programme, but the progress line is not displaying
as I require.

A past milestone has been marked as complete, however the progress line is
snagged on the left hand side of the summary bar above.

I want the progress line to not snag of the summary bar, as this indicates
the overall programme is in delay which it is not, please help.
 
S

Sai

I'm updating my milestone programme, but the progress line is not displaying
as I require.

A past milestone has been marked as complete, however the progress line is
snagged on the left hand side of the summary bar above.

I want the progress line to not snag of the summary bar, as this indicates
the overall programme is in delay which it is not, please help.

Please check if the following setting is proper:
1. Under Tools | Tracking ... Progress Lines, check the date selected
under "Always display current progress line" section.
2. Check the plan w.r.t to the progress lines needs to be drawn
"Display progress lines in relation to".
3. Make sure you have set the Status Date in Project | Project
Information

Sai, PMP, PMI-SP, MCT, MCTS
 
J

JulieS

Carlo,

Are there any non-milestone tasks under your summary bar?

When there are only milestone (zero duration tasks) underneath a
summary task, the progress on the summary task will not move
until all the milestones are complete and then the summary will
jump to 100%.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top