E
Engineer
I have entered a series of FS tasks using durations in hours and a resource
that has a 24/7 calendar. If I add up the total task duration manually it is
173 hours. But the summary task directly above these tasks shows 5.5 days.
It should be 7.2 days (173 / 24 = 7.208). Any suggetions why this is coming
out wrong? I also tried using elapsed hours instead of hours and have the
same incorrect summary task duration.
that has a 24/7 calendar. If I add up the total task duration manually it is
173 hours. But the summary task directly above these tasks shows 5.5 days.
It should be 7.2 days (173 / 24 = 7.208). Any suggetions why this is coming
out wrong? I also tried using elapsed hours instead of hours and have the
same incorrect summary task duration.