0h 0h 0h in the timesheet...

G

Gilles

In the "Task Usage" view I have resources that show assignment like this in
the timesheet:
4h 0h 0h 0h 0h 0h
Because of the 0h, the finish date for those tasks is not correct.
How can I automatically get read of this 0h and pull in my finish date.
Thank you in advance.
 
M

Manmeet Chaudhari

Hi
Try manually deleting the 0h in the task usage view and check for the finish
date then
 
W

Wiley

Are you talking about Actual Finish (as in history) or Finish as in the
planned finish date?
 
R

Ratheesh

Try the following

Make the work column from 4 to 0 and enter again the work as 4 and Try
leveling

Hope this helps
 