2003 - printing - timescale always defaults to a date way in the past

R

russellha

Is there a way to set it to the actual start of the project? Task ID 1
shows the start as Tue 9/5/06, yet the print dialog has it as Mon
5/1/06. I've looked under all the menu options and the properties under
VBA. I have no idea where the date Mon 5/1/06 is coming from. It's a
pain having to re-enter the correct date each time. Thank you, Russell
 
J

JulieS

Hi Russell,

The start date for a project file is set in Project > Project Information.
The Actual Start date of a project would be set by the Actual Start date of
the project would be the earliest of any actual start of tasks entered in
the project.

I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for the FAQs and additional information about
Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top