this is regarding start & finish dates fields.
in my project i have abot 10-20 summary tasks and all of them have on
average 7-8 subtasks.
now the problem is when increase the duration of subtask it changes the
finish date of that and start date of its successor. but it doesnt keep the
duration of the successor dependent summary task same as before, it gets
reduced and it doesnt take the finish date of that task further to keep the
duration same.
eg. 1. ABC 20 days? Fri 5/30/08 Mon 6/23/08
a 1d Fri 5/30/08 sat
5/31/08
b 12d Sun 6/8/08 Mon 6/23/08 a
2. XYZ 23.69 days? Tue 6/24/08 Wed 7/23/08 1
x 3d Tue 6/24/08 Sat 6/28/08
y 3d Sat 6/28/08 Tue 7/1/08
now when i changed the duration of subtask b to 20 days, it changed the
finish date of the b and also reduces the duration of the XYZ to 16.31 days.
is there any way that MSP 2003 keeps the duration same as before and changes
the date automatically.
i have tried my to explain the problem. if any doubts in understaing let me
know.
thanks
in my project i have abot 10-20 summary tasks and all of them have on
average 7-8 subtasks.
now the problem is when increase the duration of subtask it changes the
finish date of that and start date of its successor. but it doesnt keep the
duration of the successor dependent summary task same as before, it gets
reduced and it doesnt take the finish date of that task further to keep the
duration same.
eg. 1. ABC 20 days? Fri 5/30/08 Mon 6/23/08
a 1d Fri 5/30/08 sat
5/31/08
b 12d Sun 6/8/08 Mon 6/23/08 a
2. XYZ 23.69 days? Tue 6/24/08 Wed 7/23/08 1
x 3d Tue 6/24/08 Sat 6/28/08
y 3d Sat 6/28/08 Tue 7/1/08
now when i changed the duration of subtask b to 20 days, it changed the
finish date of the b and also reduces the duration of the XYZ to 16.31 days.
is there any way that MSP 2003 keeps the duration same as before and changes
the date automatically.
i have tried my to explain the problem. if any doubts in understaing let me
know.
thanks