D
David Schwartz
I'm using MS Project 2007. Is there an obvious reason why the Start
and Finish dates of a task might not change when I specify a
predecessor? Why wouldn't the Start date of Task 2 below be Wed
6/24/09?
TASK START FINISH PRED
Task 1 Thu 6/25/09 Fri 6/26/09
Task 2 Mon 7/6/09 Fri 7/10/09 1FS-2 days
TIA,
David
and Finish dates of a task might not change when I specify a
predecessor? Why wouldn't the Start date of Task 2 below be Wed
6/24/09?
TASK START FINISH PRED
Task 1 Thu 6/25/09 Fri 6/26/09
Task 2 Mon 7/6/09 Fri 7/10/09 1FS-2 days
TIA,
David