Robin
OK here's another one
My project starts in 01/08/2008. I've set the fiscal year to start in April
(as per UK tax year). When I create a visual report, the data sheet and
chart display this as week 29 (which is presumably calculated from January).
Why can't this be displayed as a simple date (EG week commencing 01/08/13).
Week 29 means nothing.
Any thoughts
Robin