I'm trying to create an equipment resource and assign it to the 24 hour base
calendar. However, when I choose the Base calendar in the Working Time tab,
all I see is the Standard calendar. I thought that Project comes with 3 types
of base calendars: Standard, shift work and 24X7.
I assigned a task to the 24 hour base calendar with no problem, so I'm a
little confuse as to why it doesn't work for a resource. Hopefully some one
could help
thx
Paul