D
Deb
Using a resource pool and consolidated projects. I have one contractor with
40 staff available. I need some to work 12 hour shifts around the clock and
some to work 10 hour days of a different project running at the same time.
The resource calendar takes Precedence over the base calendar for the
projects.
I want to use the resource pool to see overallocation.
What is the correct way to manage this.
40 staff available. I need some to work 12 hour shifts around the clock and
some to work 10 hour days of a different project running at the same time.
The resource calendar takes Precedence over the base calendar for the
projects.
I want to use the resource pool to see overallocation.
What is the correct way to manage this.