24 hour day and 10 hour day for 1 contractor on 2 seperate project

D

Deb

Using a resource pool and consolidated projects. I have one contractor with
40 staff available. I need some to work 12 hour shifts around the clock and
some to work 10 hour days of a different project running at the same time.
The resource calendar takes Precedence over the base calendar for the
projects.

I want to use the resource pool to see overallocation.

What is the correct way to manage this.
 
D

Deb

Have I not worded this clearly? If not let me know as I would realy like some
advice on this
 
M

Mike Glen

Hi Deb,

Welcome to this Microsoft Project newsgroup :)

I would set up resource calendars in the pool file, one for each shift.
Then in the Resource Sheet, assign the appropriate calendar, in the Base
Calendar column, to the resources. Then you can use the Resource Graph to
show availabilities.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
D

Deb

Thanks Mike for replying. Assumining you ment set up calenders in the
"change working time area" (not resource calendars). This will work I think.
Still will involve manual calculation for the overall resource, but seems to
be the only way. I appreciate having a second opinion on this.
 
M

Mike Glen

When you go to Change Working Time, create a new calendar for each shift and
assign that shift calendar to the appropriate resource - that's what I
meant!


Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top