D
DannyB
Hello all,
Can anyone please advise why a recurring 1 hour meeting is showing as 100%
or an 8 hour day for each resource on the resource graph?
The meeting is on the same days as a task with 40 % effort set for one
resource; so, on the resource graph the resource is show as 140% and
overallocated.
Yet on the little graph accessible from the resource window, the tasks show
correct as 4.2 hours????
I have been trying towo days to sort this now - please help I do not have
the time to look at it anymore, but it is university work and need to be
correct.
Thanks.
d.
Can anyone please advise why a recurring 1 hour meeting is showing as 100%
or an 8 hour day for each resource on the resource graph?
The meeting is on the same days as a task with 40 % effort set for one
resource; so, on the resource graph the resource is show as 140% and
overallocated.
Yet on the little graph accessible from the resource window, the tasks show
correct as 4.2 hours????
I have been trying towo days to sort this now - please help I do not have
the time to look at it anymore, but it is university work and need to be
correct.
Thanks.
d.