B
Bill
Hi All,
Resource is working on a job at 20% for 20 days = 4 days of work
To me that should be 0.2 days of work per day but the Resource Usage view is
showing 0.22d. This seems to be consistent across my project. Task Type is
Fixed Duration. Calendar has been set to 7.4 hour day and 37 hour week.
Start time etc have been set to make up a 7.4 hour days.
I can't spot the cause of the 0.22days. Can anyone suggest anything please?
Ta.
Bill.
Resource is working on a job at 20% for 20 days = 4 days of work
To me that should be 0.2 days of work per day but the Resource Usage view is
showing 0.22d. This seems to be consistent across my project. Task Type is
Fixed Duration. Calendar has been set to 7.4 hour day and 37 hour week.
Start time etc have been set to make up a 7.4 hour days.
I can't spot the cause of the 0.22days. Can anyone suggest anything please?
Ta.
Bill.