H
Hadi
Hi,
I have a problem with a custom calendar I created. I went to tools-->change
working time and created a 4x10 calendar with MTWTH as 10 hr working days. I
also went to tools-->options-->calendar and changed the figures there to
match that. The new working day is from 7Am to 6PMM with an hour lunch.
everthing seems OK so far. After I created nearly 20000 tasks i found out
that alot of the tasks dont start and finish like i told it. for example,
lets say I have task1 @ a 4 day duration. I thought the taks would start
monday @ 7AM and finish on Thursday @ 6PM but whaat i found out is the some
of the tasks start @ 7Am and finish at @2PM or 3PM not 6. so alot of my
resource hours are screwed up since I used units when i assigned resrouces to
these tasks and not hours. I am not sure why it did that?? any thoughts of
how the problem originated and how to fix it
many thanks
I have a problem with a custom calendar I created. I went to tools-->change
working time and created a 4x10 calendar with MTWTH as 10 hr working days. I
also went to tools-->options-->calendar and changed the figures there to
match that. The new working day is from 7Am to 6PMM with an hour lunch.
everthing seems OK so far. After I created nearly 20000 tasks i found out
that alot of the tasks dont start and finish like i told it. for example,
lets say I have task1 @ a 4 day duration. I thought the taks would start
monday @ 7AM and finish on Thursday @ 6PM but whaat i found out is the some
of the tasks start @ 7Am and finish at @2PM or 3PM not 6. so alot of my
resource hours are screwed up since I used units when i assigned resrouces to
these tasks and not hours. I am not sure why it did that?? any thoughts of
how the problem originated and how to fix it
many thanks