I am working in MS Project 2007. I am using the standard calendar, but I
have changed the working times to 7:30 am to 11:30 am and 12:30 pm to 4:30
pm, which is equivalent to 8 hours. When I list my tasks and I have a task
that is 1 day the start and finish shows Monday to Tuesday, which is 2 days.
I went back to change the working time to standard 8-5, and then the start
and finish day for a 1 day duration read Monday to Monday, which is correct.
Why aren't my new working hours working?