MS Project 2007 Calendar

T

Té

I am working in MS Project 2007. I am using the standard calendar, but I
have changed the working times to 7:30 am to 11:30 am and 12:30 pm to 4:30
pm, which is equivalent to 8 hours. When I list my tasks and I have a task
that is 1 day the start and finish shows Monday to Tuesday, which is 2 days.
I went back to change the working time to standard 8-5, and then the start
and finish day for a 1 day duration read Monday to Monday, which is correct.
Why aren't my new working hours working?
 
M

Mike Glen

Hi Té,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
J

JulieS

Hello Té,

In addition to Mike's great advice, I suggest turning on the display
of your dates to show date and time through Tools > Options, View
tab.

It's likely the default start time of your Project is 08:00 which is
causing the 1 day duration (8 working hours) to roll over to the
next day.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top