the scheduler told me that he wants that the task do not be showed in the
nonworking time in Gantt view. Can I accomplish this in project 2003?
He said sometimes he just devided one task to two tasks to accomplish this.
For example: he assigned a task, duration is 1 hour. Working time is 8:00am
to 12:00 pm, 1:00pm to 5:00pm. if the task is started at 4:30pm today, it is
showed from 4:30pm today to 8:30 am tomorrow in Gantt View. The task showed
in nonworking time too(from 5:00 pm today to 8:00am tomorrow).
Could you please tell me if I can let it not to show in the nonworking time?
Thank you very much!
nonworking time in Gantt view. Can I accomplish this in project 2003?
He said sometimes he just devided one task to two tasks to accomplish this.
For example: he assigned a task, duration is 1 hour. Working time is 8:00am
to 12:00 pm, 1:00pm to 5:00pm. if the task is started at 4:30pm today, it is
showed from 4:30pm today to 8:30 am tomorrow in Gantt View. The task showed
in nonworking time too(from 5:00 pm today to 8:00am tomorrow).
Could you please tell me if I can let it not to show in the nonworking time?
Thank you very much!