M
MCKIL
Hi,
i am experiencing a problem with Project 2007 and was hoping someone i
this community could help. Alas my installation of Project is not i
English so i hope i get all the terms right:
I want to add employee vacations to my project file and have so far
done this via resource calendar. All tasks of the project have a fixe
duration and are not effort driven. When adding a nonworking day for
colleague i don't want Project to change the start, end or duration o
the task but to spread the time over the remaining days of the task fo
this resource.
For example: If a task has a duration of 5 days and the employee take
one day off during this time Project should add 25 Percent workload t
each of the remaining 4 days.
I need the information to clear resulting overtime.
Thanks,
MCKI
i am experiencing a problem with Project 2007 and was hoping someone i
this community could help. Alas my installation of Project is not i
English so i hope i get all the terms right:
I want to add employee vacations to my project file and have so far
done this via resource calendar. All tasks of the project have a fixe
duration and are not effort driven. When adding a nonworking day for
colleague i don't want Project to change the start, end or duration o
the task but to spread the time over the remaining days of the task fo
this resource.
For example: If a task has a duration of 5 days and the employee take
one day off during this time Project should add 25 Percent workload t
each of the remaining 4 days.
I need the information to clear resulting overtime.
Thanks,
MCKI