N
natash@
I have activities that should be done in f.exp. 100 h, and have start date,
but they also have a deadline. (There are many simular activities, which
should be done simultaneously, by same group, so one activity doesn't have to
do done continuously)
If I put 100h Project calculate by itself end date and if I try to change
end date, it change back start date. How can I get all three values
undependable? Can I have two undependable dates for end, like end date and
deadline and to see them both on Ganth diagram. Sorry if this is trivial or
already asked question... I am beginner. Thanks a lot in advance, for any
help!!!
but they also have a deadline. (There are many simular activities, which
should be done simultaneously, by same group, so one activity doesn't have to
do done continuously)
If I put 100h Project calculate by itself end date and if I try to change
end date, it change back start date. How can I get all three values
undependable? Can I have two undependable dates for end, like end date and
deadline and to see them both on Ganth diagram. Sorry if this is trivial or
already asked question... I am beginner. Thanks a lot in advance, for any
help!!!