greg
I have set a deadline on an activity for the 20th of August 07. I set this
halfway through the activity was in progress. the finish date is now the 24th
of August 07 and i expect a negative slack value, if my math is correct.
However it seems to go no lower than 0. Does project detail, in terms of
negative values or days behind, for a variance on a deadline, or does it just
highlight you now have 0 days left to delay the finish of the specific
activity. Is the purpose of the slack column to say, you have this amount of
days avaiblie to slip to meet the deadline date. Is there another way to deal
with what I am trying to achieve?
Thanks,
Greg
halfway through the activity was in progress. the finish date is now the 24th
of August 07 and i expect a negative slack value, if my math is correct.
However it seems to go no lower than 0. Does project detail, in terms of
negative values or days behind, for a variance on a deadline, or does it just
highlight you now have 0 days left to delay the finish of the specific
activity. Is the purpose of the slack column to say, you have this amount of
days avaiblie to slip to meet the deadline date. Is there another way to deal
with what I am trying to achieve?
Thanks,
Greg