S
Saviz
Hi,
Scenario:
I have a task A which is 100%.
This task has resource Adam assigned to it. Adam is also assigned to few
other incomplete tasks as well.
When I change the standard rate for Adam, task A actual cost also changes
even though its already 100% complete..
Is there a way to keep previous cost when increasing a rate for a resource?
My understanding is that actuals do not change.
Thanks
Scenario:
I have a task A which is 100%.
This task has resource Adam assigned to it. Adam is also assigned to few
other incomplete tasks as well.
When I change the standard rate for Adam, task A actual cost also changes
even though its already 100% complete..
Is there a way to keep previous cost when increasing a rate for a resource?
My understanding is that actuals do not change.
Thanks