Actual Cost Changes

S

Saviz

Hi,

Scenario:

I have a task A which is 100%.
This task has resource Adam assigned to it. Adam is also assigned to few
other incomplete tasks as well.

When I change the standard rate for Adam, task A actual cost also changes
even though its already 100% complete..

Is there a way to keep previous cost when increasing a rate for a resource?

My understanding is that actuals do not change.

Thanks
 
G

Gérard Ducouret

Saviz,

You have to chnage the resource rate in its Resource information dialog, in
the Cost tab, with an Effective date....
Hope this helps,

Gérard Ducouret
 
S

Saviz

Problem Solved.

Thank you.
--
Saviz


Gérard Ducouret said:
Saviz,

You have to chnage the resource rate in its Resource information dialog, in
the Cost tab, with an Effective date....
Hope this helps,

Gérard Ducouret
 