Steve,
They are definitely Actuals. The activities that are changing are 100%
complete in the percent complete column, and have actual starts & finishes in
the actual start and actual finish column.
Since my original posting, I've found that constraints are being added to
the completed tasks that don't match the actual dates, and the durations are
zeroing out on some of the tasks, when the status date is changed. On
activities that did not change the actual dates, many also show zero days
duration, and when I add a day it will jump up to the duration of the
activity plus a day. Example 0+1 = 16 for a 15 day duration activity. The
loss of duration also happens on the tasks that do change. Some activities
get longer and some shorter.
To clean out the trash I sent the file to Access and back (.MDB). The file
went from 2931 KB to 2091 KB. I hope that helps.
No resources are loaded because they are tracked in another software.
I've looked through all of my options and found nothing unusual. I checked
with the other schedulers to match to their options, we match.
Thanks for any help,
Scott27