M
Mark@nature
I'm attempting to allocate resources to a task.
The task is expected to last 1 day. However, I do not want to be too
prescritive and state that the the task must start and complete on a specific
date, but, say, within a 5 day time frame (i.e. a working week).
Can this be modelled in MSP?
Kind regards,
Mark.
The task is expected to last 1 day. However, I do not want to be too
prescritive and state that the the task must start and complete on a specific
date, but, say, within a 5 day time frame (i.e. a working week).
Can this be modelled in MSP?
Kind regards,
Mark.