% Complete vs Actual Work
Ok....I have a task that is to start & finish on 10/27 - only 8 hours in
duration and I have 1 resource working on this task. He happens to finish
the task in 7.6hours...but when I put in the actual it changed the work hours
to 7.6 also. I would like to have the work hours to still have 8 and the
actual to say 7.6 so it will show variance of that .4 hours. Any help will
be greatly appreciated!!!!