Where would actual time be pulling from if there is no timesheet on a person?
We can't find any timesheet ect on a person yet when we look at time in
project there are over 100 hours for that person. If we delete it in project
and save it ask if we want to keep actuals and if you say yes then it puts
the time back that was deleted.
 
D

DonL

Lillian,

Any task that is marked as partially complete has those completed hours
designated as "actual" time. So, if a 5 hour task were 20% complete, it would
have 1 hour as "actual" time recorded.

Hope this helps! :)
 