actual vs projected

B

BarryH

Hi All,
I am setting up a gantt chart and I would like each task to have an actual
and projected bar for each task. Is this possible?

Thanks Barry
 
J

JulieS

Hello Barry,

Set up your project and save a baseline through Tools > Tracking Save
baseline. You may then format the Gantt chart using the Gantt chart
wizard to show the baseline bars in the Gantt. As you start to track
work, the baseline will stay stable (planned) and the gantt chart will
show actual data.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
B

BarryH

Thank you Julie

Have a great weekend

JulieS said:
Hello Barry,

Set up your project and save a baseline through Tools > Tracking Save
baseline. You may then format the Gantt chart using the Gantt chart
wizard to show the baseline bars in the Gantt. As you start to track
work, the baseline will stay stable (planned) and the gantt chart will
show actual data.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top