V
verossa
Hi All,
When I populate the actual work complete there will be ocassions when it is
greater than the baseline causing a variance (over budget). The work column
increase to reflect the actual data [I understand this].
However, I do understand why the above would alter the duration / period of
the task from 5 days to 5.35 days especially as I have chosen the task type
is 'fixed duration'.
In one scenario, I have a task requiring two departments, each consumes 40
hrs across a period of 5 days. Project automatically populates the resource
requirement (this is fine as I do not know the max resource in the
department). I have tried checking / unchecking the effort driven option
when testing but it makes no difference.
I would appreciate any assist or guidance on this matter.
TIA - Vers
When I populate the actual work complete there will be ocassions when it is
greater than the baseline causing a variance (over budget). The work column
increase to reflect the actual data [I understand this].
However, I do understand why the above would alter the duration / period of
the task from 5 days to 5.35 days especially as I have chosen the task type
is 'fixed duration'.
In one scenario, I have a task requiring two departments, each consumes 40
hrs across a period of 5 days. Project automatically populates the resource
requirement (this is fine as I do not know the max resource in the
department). I have tried checking / unchecking the effort driven option
when testing but it makes no difference.
I would appreciate any assist or guidance on this matter.
TIA - Vers